Construction Updates

Friday, June 27

The low roof waterproofing is due to be completed and the level one ceiling paint will begin on July 2. The level one buildout is 75% complete and the restrooms are 50% complete. The exterior work on the Matty's Closet area is 80% complete.

The Valera NEST Construction as of 6/27/25

Friday, June 20

Level one interior work and drywall installation are in progress. The phase II north site concrete work has been completed and is pending final inspection.

The Valera NEST Construction as of 6/20/25

Friday, June 13

The phase II north site concrete work has been completed and is pending final inspection. Work on the low roof waterproofing and level one interior are ongoing.

The Valera NEST Construction as of 6/13/25

Friday, June 6

The final pour for the north site concrete is scheduled for June 10. Work on the level one interior continues.

The Valera NEST Construction as of 6/6/25

Friday, May 30

Work on the level one interior and north site concrete continue. The South deck parapet plaster installation is complete and painting will be scheduled.

The Valera NEST Construction as of 5/30/25

Friday, May 23

Work on the level one interior and north site concrete continue. The South deck parapet plaster installation is complete and painting will be scheduled.

The Valera NEST Construction as of 5/23/25

Friday, May 16

Work on the level one interior and north site phase II concrete continue.

The Valera NEST Construction as of 5/16/25

Thursday, May 8

The South deck parapet plaster installation is complete and pending paint. Work on the level one interior and north site concrete continue.

The Valera NEST Construction as of May 8, 2025

Friday, May 2

Work on the level one interior continues along with plaster installation on the south deck parapet.

The Valera NEST Construction as of 5/2/25

Friday, April 25

The south deck concrete pours are complete. Work on the level one interior continues.

The Valera NEST Construction as of 4/25/25

Friday, April 11

Work continues on the level one interior. The south deck rebar is installed a the area is prepped for concrete pouring.

The Valera NEST Construction as of 4/11/25

Friday, April 4

Work continues on the level one interior. Steel plate infill is completed. The south deck is prepped for concrete pouring.

The Valera NEST Construction as of 4/4/25

Friday, March 28

Level one interior and south deck work continues. Underground drainage is installed and backfilled.

The Valera NEST Construction as of 3/28/25

Friday, March 21

Level one interior and south deck work continues. Drainage installation on the north side is in progress.

The Valera NEST Construction as of 3/21/25

Friday, March 14

Level one interior work ongoing, including steel plate fastening, framing, overhead electrical, mechanical duct and restroom plumbing.

Valera NEST Construction as of 3/14/25

Friday, March 7

Level one interior work continues, including Matty’s Closet steel installation, mechanical ducts and water lines.

The Valera NEST Construction as of 3/7/25

Friday, Feb. 28

Structural upgrades complete. Work on the level one interior continues. 

The Valera NEST Construction as of 2/28/25

Friday, Feb. 21

Structural upgrades and interior framing continue. Mechanical duct installation in progress. 

The Valera NEST Construction as of 2/21/25

Friday, Feb. 14

Structural upgrades and interior work continue.

The Valera NEST Construction as of Friday, Feb. 14

Friday, Jan. 31

Work on The Valera NEST interior continues along with structural upgrades.

The Valera NEST Construction as of 1/31/25

Friday, Jan. 24

The roof tile installation and several concrete pours, including infill slabs, the pool equipment slab, north exterior seat walls and the trench in the locker room, are complete. Structural upgrades continue.

Valera NEST Construction as of 1/24/25

Friday, Jan. 17

The south deck high-strength grout pour is completed and the area is being prepped for waterproofing. Additional level one framing and plaster wall infills continue.

Valera NEST Construction as of 1/17/25

Friday, Jan. 10

Structural upgrades continue, including level one framing installation and plaster wall infill. Roof tile installation has been delayed due to high winds and the south deck grout pour is in progress.

Valera NEST Construction as of 1/10/25

Friday, Jan. 3

Structural upgrades and roof installation continue. Excavation for the new tree irrigation line is in progress and the north exterior concrete pouring has concluded.

Valera NEST Construction as of 1/3/25

Friday, Dec. 13

Structural upgrades and roof installations continue. 

Valera NEST Construction as of 12/13/24

Friday, Dec. 27

Roof installation continues, along with structural upgrades. The north exterior site (in front of Subway) rebar installation is complete and will be followed by concrete pouring.

Valera NEST Construction as of 12/27/24

Friday, Dec. 6

Landscape remediation and the demolition of the pool basement slab have been completed. The roof tile installation and interior wall layout are in progress.

Valera NEST Construction as of 12/6/24

Friday, Nov. 27

Fire lane and pool deck concrete pours and high roof skylight installs have been completed. Demolition of the pool basement slab is in progress along with weather protection.

Valera NEST Construction as of Nov. 27, 2024

Friday, Nov. 15

Structural upgrades, roof installation and South Patio waterproofing continue.

Valera NEST Construction as of Nov. 15, 2024

Friday, Oct. 25

The fire water trench backfill is complete. Structural upgrades, roof installation and prepping the South Patio for waterproofing continue.

Valera NEST Construction as of 10/25/24

Friday, Oct. 18

Structural upgrades, roof waterproofing and fire water trench backfill continue.

Valera NEST Construction as of Oct. 18, 2024

Friday, Oct. 11

Structural upgrades and the fire water line installation continue. Waterproofing on the roof and South Patio deck has commenced.

Valera NEST Construction as of Oct. 11, 2024

Friday, Sept. 27

The trench for the new fire water line install as well as the interior and exterior demolition are ongoing. The backfill of the water line trench is complete and roof cutouts for skylights are in progress.

Valera NEST Construction as of 9/27/24

Friday, Sept. 20

The exterior and interior demolition are ongoing. The backfill of the first level exterior water main is ongoing and fire line trench has been laid out at the pool deck.

Valera NEST Construction as of Sept. 20, 2024

Friday, Sept. 13

The exterior and interior demolition and the trench for the new fire water line install are ongoing.

Valera NEST Construction as of Sept. 13, 2024

Friday, Sept. 6

The demolition of level one kitchen and exterior slab is ongoing.

Valera NEST Construction as of Friday, Sept. 6, 2024

Friday, Aug. 30

South exterior slab demolition and cut and cap ductwork on the interior (level one) completed. Wood framers’ material delivered.

Valera NEST Construction as of Aug. 30, 2024

Friday, Aug. 23

Demolition continues on the exterior.

Valera NEST Construction as of Aug. 23, 2024

Friday, Aug. 16

The demolition contractor completed demolition of the ductwork and interior walls inside the future Valera NEST.

USU Valera NEST Interior Under Construction

Friday, Aug. 2 

The demolition contractor completed demolition of the ductwork and interior walls inside the future Valera NEST.

Valera NEST Construction as of Aug. 2, 2024

Friday, July 26 

The demolition contractor completed demolition of the high roof and began demolition inside the future Valera NEST.

Valera NEST Construction as of July 26, 2024

Friday, July 19 

The contractor set up construction fencing around the Valera NEST project site and installed project signage. The demolition contractor began removing concrete roof shingles.

Valera NEST Construction Site as of July 19, 2024